8 men complete a work in 40 days. How many days will be taken to complete the samed work if 2 more men join them.

Respuesta :

rpband00
rpband00 rpband00
  • 04-04-2018
Hello there,

There were 8 men who completed a task in 40 days. If you divide 40/8 that is 5 so it took them 5 weeks to complete this task.

Now if you add two more men, that makes it 10 men to complete the work in 50 days. If you divide 50/10 that is 5.
10 days

Hope this helped!

Answer Link

Otras preguntas

( Brain + 100 points ) A triangle has an area of 30 cm squared. What might the base and height be? Give 3 examples.
Find a polynomial f(x) of degree 3 with real coefficents and following zeros. -4,4i
What is the volume of this sphere? Use ≈ 3.14 and round your answer to the nearest hundredth. 10 m cubic meters
Which is the BEST example of the kind of mechanics that are studied in sports biometrics?
21. Identify the sentence in which the underlined verb does not agree with its subject. ONeither of the twins “are”interested in sports. OBoth of them “have” ma
Please help.(check image)
Two functions are given below. Make sure to explain!
Eating Insects to Feed the World, could mealworms be a more sustainable protein source than beef? Why?
what is the answer for 0.32+12.965+1.1 and could you explain how you got the answer​
How many solutions does the system of equations have? y=-2x+3 y = x² - 6x +3