In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.

Respuesta :

MissPhiladelphia
MissPhiladelphia MissPhiladelphia
  • 14-02-2017
The choices can be found elsewhere and as follows:

A.initiating
B.planning
C.monitoring/controlling
D.closing
E.assessment

I believe the correct answer is option B. 
In the execution phase of a project's life cycle, activities are guided by decisions that were made in the planning phase. Hope this answers the question.
Answer Link

Otras preguntas

Please answer the question of saying yes or no. 1) Does life exist on Mars? 2) Is Classical music better than Rock? 3) Do angels exist? 4) Is affirmative actio
When bone grows in thickness, which part of the bone grows and which part of the bone is broken down? *
simplify -26+7r-15p-7p
What is the reciprocal of -7/9?
Please help I just need two more pg last time i did this people complained not enough points so i put over 10 ;w; Please help on this i already wrote one pg.
WHO WANNA START SOMETHIN
a vector is represented as a ____​
Trees begin from tiny seeds, with a mass of a 2-3 grams, and yet an adult tree can weigh many thousands of pounds. If matter cannot be created (Law of Conservat
Which climate zone has the lease amount of diverse plant life
how did early pharaohs unite egypt.