15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

What is the value of a in the equation , when ? 3 15 21 39
✹ BRAINLIEST ANSWER WILL BE CHOSEN ✹ Put the four major turning points in world history in the correct order. *I'll mark brainliest after reviewing completed pr
What is f(g(x)) for x > 5?
What is the role of consumers in determining what is produced in a market economy? A) Consumers work in the production of goods. B) Consumers set the prices f
which of the statements about the following quadratic equation is true? 6x^-8=4x^2+7x
match the following actions with the system in which government performs them.
While the federal government was already required to do so (according to the Fifth and Sixth Amendments to the U.S. Constitution), the case of Gideon v. Wainwri
what is a dependent clause
In which case will the object move due to an unbalanced force
Which were the first people to use spears with flint points to hunt? A. the Woodland Indians B. the Paleo Indians C. the Archaic Indians D. the Late Pre