If 10 workers, working for 4 hours complete the work in 12 days, in how many days will 8 workers working for 6 hours complete the same work?

Respuesta :

mariyamzuha123
mariyamzuha123 mariyamzuha123
  • 03-05-2021

Answer:

As per the question, 10 workers working for 4 hours a day complete their work = 12 days. 1 person working for 1 hour a day complete the work = 12×10×4 days. Thus, the 8 persons working for 6 hrs a day complete their work in 10 days.

Step-by-step explanation:

hope it helps

please mark brainliest

Answer Link

Otras preguntas

Which pair of triangles is congruent by ASA?
Write a method called doubleit that accepts a string parameter and returns that string concatenated with itself. for example, if the parameter is "program", the
Is achilles' response to agamemnon's offer rational?
BRAINLIEST!! THANKS!! STARS!! Find ONLY the areas of the polygons
After world war ii, the eastern half of germany was called the ________.
Two students described a part of Earth's innermost layer. Daniel: Densest part Joshua: Has highest temperature and pressure Which part of the innermost layer
Solve 3x ^2 + 2 = 11 - x ^2
In the 1860 election, how many different presidential candidates won electoral votes?
Who feels excited when Aslan's name is first mentioned? A. Susan B. Lucy   C. Edmund D. the White Witch
Which of the children described below is likely to experience the most difficulty in school?